The following is a guest post from Sam Williams at Matechi.com. We met at Autodesk University 2026 at a Pirros mixer. He is working on some cool stuff, and I asked if he could share what he is working on in a few posts here on BIM Chapters. Here is the first installment...
On Tuesday, the engineers made 36 cooling pipes one size
bigger in the Revit model. On Thursday the fabrication shop was still welding
the old size, and that gap is where a lot of construction rework comes from.
We caught it, and I want to show you how, because it touched nearly every step between a model and a finished building. At Matechi we build AI agents for the built world, and this change was a good chance to see them work together on one data center, Lone Star 48 Hall 2.
Figure 1. Hall 2, the liquid-cooled data center we follow, built up
system by system in the model. [fig-01 · film 0:02–0:15, sped up · scroll page stops 1–5]
keep reading...
Tuesday: a spec check finds the problem
Hall 2 is cooled with liquid, and the cooling distribution
units, or CDUs, sit in one room. On Tuesday the engineers found that the 36
pipes branching off them were too small, because the water moved at about 2.2
meters per second against a limit of 2.0. So they went from DN 150 to DN 200,
which is roughly 6 inches to 8.
Before that change went anywhere, we wanted to know what
else in the building it touched. In this case we used Matechi
QA/QC, a model checker for Revit that reads your spec and checks
every element against it. The spec had six rules, one of them C-01, which says
DN 200 minimum. Claude reads the spec, plain code does the checking, and a
person approves it. It went through 3,271 elements in 7.1 seconds and came back
with 110 critical findings, each one naming the rule it broke. By hand that's
about six hours of clicking, by our estimate.
Where no spec covered the chilled water system, it stopped and asked a person instead of guessing, and it only previewed the fix to DN 200. So the engineers made the change in Revit themselves, which is how we wanted it.
Figure 2. Matechi QA/QC checks a whole Revit model against the spec in
7.1 seconds. [fig-02
· film 1:04 · stops 14–15]
The fix runs into a cable tray
Bigger pipes need more room, and the new ones ran into the power cable tray 18 times. Revit has clash detection of its own, the Interference Check, and it found those 18. What it doesn't do is tell you what to move, so we also ran Matechi Clash, which finds BIM clashes and proposes how to resolve them. It found the same 18 among 2,755 clashes in the whole model in under two and a half minutes, and it said to move the tray and not the pipe, because a riser pulls its whole stack along with it. The tray moved 50 mm, and the same six rules passed.
Figure 3. Matechi Clash resolves BIM clashes by suggesting what to move,
and Revit's Interference Check agrees. [fig-03 · film 1:55–2:09 · stops 27–30]
That meant we walked into the coordination meeting with the
fix already on the table.
Thursday: the shop is welding the old size
The gallery gets built off site in pieces, and every piece has to connect to its neighbor at the right pipe size. The cooling unit built for the old size had 6-inch connections and the rack needed 8-inch ones, so it wouldn't fit, and the revised one did.
Figure 4. The old cooling unit doesn't fit the rack, and the revised one
does. [fig-04
· film 2:58 · stops 42–43]
The next question was what the change did to the shop itself. For the factory layout we used Matechi Factory, which plans a fabrication layout for modular construction from the shop's own documents. The plan came from three of them, an operations request, an equipment list and a time study. When the revision landed, it read all three again, listed every value that changed, and re-ran the layout. All 22 of 22 paths stayed clear, four stations moved, and the drawings were redrawn, L-102 for the moves and L-101 for the plan. The robotic weld cells got wider pads for the bigger pipe.
Figure 5. Matechi Factory re-plans a fabrication shop layout from a revised document. [fig-05 · film 3:26–3:45, in three cuts · stops 48–50]
Figure 6. The L-102 drawing lists each station move, generated from the
revised layout. [fig-06
· still only · film 3:46 · stop 51]
Then there was Thursday itself. The model comparison found
the 36 pipe sections still on the old version, a person held them and reissued
them, and Pod Traveler, which follows each modular unit
from the shop to the field, showed the new version at the weld station before
the first weld.
The road, the crane and the site
What ships is sized by the road, and no drawn door takes a 3.1 m rack. So the roof came off and a crane lowered each rack between two joists with 92 mm to spare on each side.
Figure 7. A crane sets a prefabricated rack through the roof opening, 92
mm clear on each side. [fig-07
· film 4:22 · stops 57–59]
Once it was built, we wanted to know whether it matched the model. A technician walked the gallery with a phone and took 36 photos, and Field Evidence, our as-built tool, placed every one on the 3D model to within 9.8 mm. It flagged one valve from old stock that was DN 150 where the design said DN 200. The valve got swapped, photographed again and closed, with the record pointing back to the spec row. If you'd like to try an as-built check like this on your project, tell us about it.
Figure 8. Field Evidence checks a build against the Revit model by placing site photos on it. [fig-08 · film 4:50 · stops 63–65]
Figure 9. The issue closes with the before and after photos once the
valve is swapped. [fig-09
· still only · film 5:10 · stop 68]
Where you can learn this on one real project
Everything above happened on one data center, and that same
project is now a course. The Data Center Common Core is a data center
construction course that follows one real project from owner requirements
through systems, coordination, construction, commissioning and handover. It's
taught in our Data Center Delivery Lab, for architects and engineers who work
on data centers or want to, and it's in development now. Join the course interest list and we'll tell
you when the first cohort opens.
If you want to see the whole story end to end, you can scroll
through it or watch the film. Somewhere in your own
projects, a late change is already on its way to a place that doesn't know yet,
so which handoff would you test first?
A few quick answers
Does Revit have clash
detection? Yes, the Interference Check finds clashes, and a tool like
Matechi Clash goes on to suggest the fix.
What does the data
center course cover? One project from owner requirements to handover,
including commissioning.
Who is it for?
Architects and engineers who work on data centers or want to.